Wednesday, July 9, 2008

WORK HAS RESUMED!! Final Plumbing Underway

Work resumed yesterday 7/8/08 on the house after a 4 week stand still. The plumbing crew came in and started work on the final plumbing. They installed sinks, faucets, toilets, hot water tank, sump pump, PEX water grid, outside spickets, & other misc. plumbing items.  The electric crew is supposed to be in today to install light fixtures, outlets, and switches.

The installation of the septic has yet to occur. There's been a few delays with that, but it should go in by next week if all goes well.

The flooring should go in next week as well as some minor fix-ups & finishes that need to be taken care of. If all goes well and we pas inspections and gain an occupancy permit, we should be moving in on Saturday, July 26th. 